Pre-start meetings and site inductions: what to record under CDM 2015

By Chris M, Director, AI Metric Ltd · Published · Sources checked · 3 minute read

The short answer

CDM 2015 requires the principal contractor to make sure a suitable site induction is provided and to consult and engage with workers on health, safety and welfare. A good record of a pre-start meeting, induction or briefing shows who attended, what was covered, which method statements and risk assessments were briefed, and the questions raised and answered.

The duties behind the meetings

The Construction (Design and Management) Regulations 2015 put specific duties on the principal contractor during the construction phase. Regulation 13 requires them to make sure a suitable site induction is provided. Regulation 14 requires them to make and keep arrangements for workers to cooperate on health, safety and welfare, and to consult workers or their representatives in good time on matters that may affect them. The HSE's guidance on the regulations, L153, explains how these duties work in practice.

Pre-start meetings with a subcontractor before a package begins, daily activity briefings and toolbox talks are the everyday ways those duties are met. The regulations do not prescribe a form for the record, but being able to show who was told what, and when, is how a contractor shows the briefing happened.

What a good record holds

RecordWhat it should show
Site inductionWho was inducted, by whom, on what date, and the site rules and hazards covered
Pre-start meetingThe package, the companies and people present, the method statement and risk assessment briefed, interfaces with other trades, permits, plant, and questions raised
Daily activity briefingThe day's work, the hazards and controls for it, and who attended
Toolbox talkThe subject, who gave it, who attended

Recording the meeting itself

A pre-start meeting often agrees things that matter later: the sequence, who provides access, what is in and out of the package. Minutes written from a recording capture those agreements as they were said. If you record, tell everyone at the start, and follow your company's rules on recording.

In Note Metric you can set the meeting type (DABS, Inspection, Progress Meeting and others, or your own), so the minutes come out in the right shape, and a notice to read or send before the meeting is in Settings.

Questions

Do attendees have to sign the induction or briefing record?

CDM 2015 does not say so, but most contractors ask for a signature or a sign-in because it is the simplest proof of attendance. Keep the signed sheet with the minutes or briefing record.

Is a recording a substitute for a signed briefing sheet?

Not on its own. A recording shows what was said; a sign-in shows who was there and confirms they received the briefing. Use both where the risk justifies it.

How long should induction and briefing records be kept?

Your company's records policy decides. Keep in mind that health and safety records can be asked for long after a project ends, and that any personal data in them should be kept only as long as it is needed.

Sources

  1. The Construction (Design and Management) Regulations 2015, regulation 13: the principal contractor's duty to make sure a suitable site induction is provided
  2. The Construction (Design and Management) Regulations 2015, regulation 14: the principal contractor's duty to consult and engage with workers
  3. HSE, Managing health and safety in construction, L153: the HSE's guidance on the regulations
  4. HSE, CDM 2015: the HSE's overview of the regulations and duty holders

Our summaries of these documents are not their wording: read the source before relying on it. This guide is general information, not legal advice for a particular case. Note Metric and AI Metric Ltd are not affiliated with or endorsed by any body named here.

About the author

Chris M, Director of AI Metric Ltd, has spent more than twenty years in Tier 1 construction delivery, working across commercial, procurement, design and engineering teams as well as operations. He builds Note Metric for the meetings and walk-rounds he has run himself. More about Chris.

Record it once. Get the minutes.

Note Metric records meetings in the room, on Teams, Meet or Zoom, and site walk-rounds, then writes the minutes, actions and survey draft for you. Every line plays back the moment it was said. Recording and keeping meetings on your iPhone is free; plans from £8.99 a month add transcripts, minutes and sync.

Sign up and start See plans and prices