How to write construction meeting minutes that stand up later

By Chris M, Director, AI Metric Ltd · Published · Sources checked · 4 minute read

The short answer

Good construction minutes record who attended, what was decided, what each person agreed to do and by when, and the risks raised, in plain words, issued the same day and agreed by the people who were there. Record what was said rather than what you hoped was said, and keep the evidence behind each line so it can be checked later.

What minutes are for

Minutes are the agreed record of a meeting. On a construction project that record often outlives everyone's memory of the meeting itself: a programme argument, a variation or a defect claim can turn on what was said in a progress meeting months or years before. The Society of Construction Law's Delay and Disruption Protocol puts records first among its core principles, and asks the parties to agree at the start what records will be kept. Minutes are one of the records that do the most work.

So minutes have two jobs. They tell the team what happens next, and they leave a record someone can rely on later. A set of minutes that does only the first job is a to-do list.

What every set of minutes should record

PartWhat to writeWhy it matters later
HeadingProject, meeting type and number, date, time, place or call linkPuts the record in sequence with the others
AttendanceName, company and role of everyone present, and apologiesShows who heard what
Previous minutesAgreed, or the corrections asked forCloses the last record
ItemsOne numbered item per subject, kept under the same number while the subject is openA subject can be followed through every meeting
DecisionsWhat was decided and who decided itThe single most argued point later
ActionsWho, what, by whenTurns talk into commitments
Risks and early warningsWhat was raised and by whomShows when a problem was first known
Next meetingDate and placeKeeps the series going

How to word it

Write what was said, not what you think it meant. "The subcontractor said the steel would arrive on 14 March" is a record; "Steel delivery confirmed" is an interpretation, and the difference matters if the steel arrives in April.

Name the person, not just the company, wherever someone committed to something. Give an owner and a due date only where one was actually given: an invented date in the minutes is worse than none, because it reads as agreed. Use the project's own terms (gridlines, levels, package names) so the record can be searched later.

Keep opinions out unless they are part of the record. If someone disagreed with a decision, record that they disagreed; that is a fact.

Issue them while memories agree

Minutes issued the same day are corrected while everyone still remembers the meeting. Minutes issued a fortnight later are argued about. Ask for corrections by a set date, and record at the next meeting that the minutes were agreed or what was changed.

A recording helps here. When the minutes are written from a transcript, any line can be checked against what was actually said instead of against two people's memories. Note Metric writes minutes from the transcript alone and every timed line plays back the moment it came from; a line it could not match to the recording is marked to check against the transcript.

Questions

Who should write the minutes?

Usually the person chairing or their nominee, or the party the contract makes responsible (on many contracts that is the project manager or contract administrator). What matters most is that one named person issues them and handles corrections.

Should minutes be word for word?

No. Minutes are a summary of what was decided, agreed and raised. Keep the transcript or recording if you need the exact words, and say in the minutes where the record is kept.

Do minutes have to be signed?

Few contracts require it. What helps is a clear trail: issued on a date, corrections invited by a date, agreed or corrected at the next meeting. The Delay and Disruption Protocol suggests records are, where practicable, agreed between the parties' representatives.

What if someone disputes the minutes?

Record the disagreement and the correction asked for, then settle it against the evidence. If the meeting was recorded with everyone's knowledge, play back the moment in question.

Sources

  1. Society of Construction Law, Delay and Disruption Protocol, 2nd edition: core principle 1, programme and records
  2. Fenwick Elliott, The SCL Delay and Disruption Protocol: a second edition: summary of the record keeping guidance, including agreeing records between the parties
  3. CIOB, Code of Practice for Project Management for the Built Environment, 6th edition: the CIOB's reference on project management practice, including meetings and reporting
  4. NEC, How NEC4 ECC guarantees a good performance for clients: early warning meetings and the register the project manager keeps

Our summaries of these documents are not their wording: read the source before relying on it. This guide is general information, not legal advice for a particular case. Note Metric and AI Metric Ltd are not affiliated with or endorsed by any body named here.

About the author

Chris M, Director of AI Metric Ltd, has spent more than twenty years in Tier 1 construction delivery, working across commercial, procurement, design and engineering teams as well as operations. He builds Note Metric for the meetings and walk-rounds he has run himself. More about Chris.

Record it once. Get the minutes.

Note Metric records meetings in the room, on Teams, Meet or Zoom, and site walk-rounds, then writes the minutes, actions and survey draft for you. Every line plays back the moment it was said. Recording and keeping meetings on your iPhone is free; plans from £8.99 a month add transcripts, minutes and sync.

Sign up and start See plans and prices